Line
Stopping
The following
is the basic procedure:
1. Line
stop equipment is installed on the temporary tapping valve and the
valve is opened.
2. Line stop head enters the pipeline through the hot tap connection.
3. Temporary seal is achieved and pipeline flow is stopped (unless bypass is
in place).
4.
Repair, alteration, or relocation of the pipeline is performed.
5.
Line stop head is removed from the pipeline through the hot tap
connection.
6. Temporary valve is closed and the line stop equipment is removed.
7. Completion plug is installed on the tapping machine.
8. Tapping machine is installed on the temporary tapping valve.
9. Temporary tapping valve is opened and the completion plug is installed in
the branch of
the line stop fitting and locked into position.
10. line stop equipment and temporary valve are removed from
the line stop fitting.
11. Blind flange is installed on the line stop fitting.
|